Latest updates 

Aug. 27, 2026

Project map
Schedule / Phasing plan

Phase 1

  • Week of Aug. 24
    •  Utility replacement work is complete.
    • This week, the concrete contractor will be working on the installation of curbs, driveways, and sidewalks.
  • Weeks of Aug. 31 and Sept. 1
    • Concrete installation could continue into the following week.
    • The grading contractor will be fine-grading the gravel base.
  • Week of Sept. 7
    • Paving of the first layer of bituminous street pavement is tentatively scheduled for the week of Sept. 7. The exact date has not yet been determined.
  • After paving is complete, the contractor will begin grading the boulevards and adding new topsoil. Sod installation will follow.

Phase 2

  • Weeks of Aug. 24 and 31
    • The utility contractor will be working on water service replacements on the 2800 and 2900 blocks of Colorado Avenue over the next couple of weeks. Replacement of storm and sanitary sewer structures is also ongoing.
    • A temporary water system will be set up on the 2900 block of Brunswick Avenue within the next week or two.
  • Week of Sept. 8
    • The grading contractor will continue rebuilding the road by excavating and grading the subbase material in preparation for curb installation.
  • Week of Sept. 14
    • Curb installation is tentatively scheduled to begin this week, weather permitting.

Work in Phases 3 and 4 of the project will begin later this summer. The city will provide additional updates on the anticipated start dates for each phase as the work gets closer.

Private improvements in the right of way

GMH Asphalt will be working in the public right of way. If you have private improvements such as underground sprinklers, electrical wiring, perennial gardens, or invisible fences within 15 feet of the curb, they are likely in the public right of way. Removal and reinstallation of these items are the property owner's responsibility.
Plan to remove these items from the public right of way as soon as possible. Private improvements that are not removed may be damaged during construction. Property owners are responsible for repair or replacement of damaged items. If you have questions, contact the project coordinator.

What to expect during construction

In the video below the city explains a typical construction process, service impacts, property impacts, restoration activities, private utilities, what the end of construction looks like and more.

 

Project background
Public engagement